The information stage

The information file: what it gives you
and how to read it properly

An information file is the document in which the licensing authority translates the planning that applies to an area into a single plot: how much may be built, where, and on what conditions. No permit application can be opened without a valid one, and every line in it later becomes a line checked against your drawings.

An open building permit information file on a desk beside a surveyor map and an architectural drawing

What an information file is and why nothing starts without one

The information file (תיק מידע) is the committee's written ruling, obtained before anyone pays for design, on every point where the planning applying to the plot is ambiguous. It is not an opinion but the data set your drawings will be checked against.

It is issued by the licensing authority (רשות הרישוי) after internal circulation to the departments, and without its number no permit application can be opened.

A zoning plan (תב"ע) covers a whole area in general language, and three or four plans from different years often apply to one plot. The file is the local planning and building committee's (ועדה מקומית) ruling on which prevails, and on what the spatial design guidelines (הנחיות מרחביות) add.

If one approved plan applies and nothing is deposited, the figures are stable. If the file points to a deposited plan, the design must be tested twice, against the position in force and the position expected, adding 5 to 15 per cent to sketch-stage hours where that plan changes land use or density.

Validity runs around a year and varies by committee and application type. Figures reflect the planning position on the day of issue, so design built on an expired file needs correcting. The order is placed by the licensed application editor (עורך הבקשה).

How the file is ordered and what happens before it arrives

Ordering is an administrative procedure with a fixed input list, and one missing item returns the request before it is opened. Settle the list of required documents with the specific committee first.

  1. A current signed map from a licensed surveyor (מפת מדידה), in the authority's format.
  2. A land registry extract (נסח טאבו) or a rights confirmation from the Israel Land Authority.
  3. Retrieval of the existing structure's permits and drawing sets (גרמושקה) from the archive.
  4. Opening the request in the system by the editor, describing the substance in exact words.
  5. Approval by the rights holder and payment of the fee, without which the request sits.
  6. Internal circulation: infrastructure, traffic, landscape and sanitation comment to the compiling officer.
  7. Compilation and issue: one document with appendices, a situation map and approving bodies.

In most committees the answer returns within 20 to 45 working days from payment. A plot inside a single plan with a compliant survey map sits at the low end; a deposited plan, unscanned permits or an outside body push it higher.

The recurring failure here is a vague substance description. An application logged as building addition yields a generic file addressing neither basement nor parking; one naming a second storey plus a basement addresses both. Every element that will appear in the drawing set needs its own line: a supplementary request costs 15 to 30 working days.

What exactly appears inside the file

The file has three layers and only one is written in numbers: the planning in force, the spatial design guidelines, and the conditions and approving bodies. The last two are prose and get skimmed, though all three bind equally. Read it backwards: approving bodies set the timetable, the rights table sets the budget.

  • Land use and the plans in force, and which prevails on each subject.
  • The rights table: main and service area, coverage, storeys, height and dwelling units.
  • Building lines on every side, including any planned road not yet laid.
  • Design guidelines: finishes, roof pitches, fences and the position of plant.
  • The parking standard, the entrance position and any payment in lieu.
  • Protection and safe room requirements, with the authorised body's approval as a condition.
  • Infrastructure: water, sewage and electricity connections, drainage and governing levels.
  • Required surveys and consultants: soil, traffic, mature trees and accessibility.
  • External approving bodies and the point at which each enters.

The guidelines are read late, and missing them is expensive because it surfaces once elevations are drawn. They are absent from the zoning plan, differ between neighbourhoods, and are sometimes held in a separate document on the committee website, which is part of the file: download it and keep a dated copy.

Where the rights table and the attached plan provisions conflict, the provisions govern, a point to clarify in writing rather than resolve alone.

A map of the file: what each component decides

The components sorted by what each decides, the check to run the day the file arrives, and the price of missing it.

ComponentWhat it decidesImmediate checkPrice of missing it
Rights tableMain and service area permitted, and whether the basement counts insideRegistered or surveyed area behind the percentagesA cut of 10 to 40 sq m and a floor plan redo
Building linesWhere the structure may stand and how the envelope shrinksMeasured from the boundary or a planned road axisMoving the building late, 3 to 8 weeks of redesign
Coverage and storeysMaximum footprint and how far the building may riseWhether a top storey setback is compulsoryFacade rework after consultants were priced, 2 to 5 weeks
Design guidelinesAppearance, fences, roofs and the position of plantA guidelines document referred to but unattachedA correction demand at design review, 2 to 6 weeks
Parking standardNumber of spaces and any payment in lieuDerived from dwelling units or from built areaLosing a room, or 10 to 25 sq m given to vehicles
Approving bodiesWho must approve and at which stage each entersWhether approval needs a submission outside the systemA 4 to 8 week wait that could have started on day one
InfrastructureConnection points, drainage and governing levelsWhether the survey covers pavement levels and gulliesA further survey and site redesign, 2 to 4 weeks

What the information file does not contain

The file states what is permitted on the plot, not what will be approved for you. The distance between those two statements produces most of the disappointment at submission.

No final area schedule

The file gives a framework in percentages, not an area table. Turning it into a real number is the editor's work, once the area rules meet the design: what counts as main area, what as service, and what happens with balconies and the safe room (ממ"ד). Two architects can land 10 to 40 sq m apart from one file, the upper end typical of many balconies and a basement whose outline differs from the structure above. The method is in the guide to calculating building rights.

No ruling on reliefs or levies

If you intend to exceed the framework, the file will not say whether a relief (הקלה) will be granted; at most it notes the committee may consider one. That falls after publication and an objection window. Nor does the file carry a betterment levy (היטל השבחה) assessment: it is prepared later and conditions the permit, not the submission.

Two further absences: the file neither checks what stands on the ground against the permits on record nor touches title. Order the registry extract and the permit cross-check in the same week as the file, so both run alongside the wait.

How the file governs every design decision that follows

Every line in the file later becomes a line on a checklist. The application is tested against threshold conditions and then at design review (בקרת תכן), where the reviewer invents nothing: he compares what you submitted with what the file said. A mismatch is a correction demand rather than a refusal, but each round returns the file to the editor and adds 2 to 6 weeks.

From that follows a work order that saves money. Consultants the file requires are engaged after it arrives, and within that there is a hierarchy: soil and traffic precede the structural engineer, because their conclusions move the building's position and the entrance level.

If design was commissioned before the file, assume 20 to 50 per cent of the work will be discarded. What raises the figure is a plot carrying several plans, an existing structure on old permits, or design that already reached detailed drawings. What lowers it is stopping at a massing sketch.

The file sets the timetable as well as the content. An external body entering only at design review adds one to two months, while the same body applied to on the day the application opened runs in parallel and adds nothing. That order of submissions is part of managing the process.

A worked example: from framework to the real number

A generic plot: 500 sq m of residential land, 20 by 25 metres. The plan permits 60 per cent main area, 30 per cent service, 40 per cent coverage and two storeys above a basement. The file adds building lines of 5 metres front, 4 rear and 3 each side, plus a 2 metre setback on the upper storey. The sketch had a 180 sq m basement.

  • Rights on paper: 300 sq m main, 150 sq m service, 450 in total.
  • Coverage: 200 sq m per storey, 40 per cent of 500.
  • Envelope: 25 less 5 less 4 is 16 metres by 14, or 224 sq m, so coverage binds.
  • The upper storey setback leaves 196 sq m, so 396 sq m above ground.
  • Service that must sit above ground: safe room 15, stair core 20, balconies 24, or 59.
  • Rights used above ground: 300 plus 59, or 359 sq m inside 396.
  • Left for the basement from 150 sq m of service area: 91 sq m.

The 180 sq m basement is not available; the shortfall is 89 sq m. The ways out are cutting it to 91 sq m, checking whether the plan allows basement area outside the rights, or requesting a relief. That choice falls at sketch stage, since it moves the stair core and the entrance level.

The 37 sq m between 359 and 396 are envelope without rights. What sets the budget is how the 150 sq m of service area is split: every service metre above ground comes off the basement one for one, so a lift or another balcony cuts it. The file also required a soil survey for any basement, 2 to 5 weeks.

What actually goes wrong when people read the file

Reading the table and skipping the words

The failures here are not of knowledge but of selective reading, and four repeat. The owner forwards the square metres to the architect, leaving unread the paragraphs on appearance, roof pitch and the position of air conditioning units. It surfaces at design review as a demand to redraw elevations, once consultants have been paid: 2 to 6 weeks.

The plot area differs between documents

The registry extract says 500 sq m, the survey map measures 483, and the file calculates rights without saying which it used. Seventeen square metres are roughly 10 sq m of main area, which is a room. A written query returns within 1 to 3 weeks; after submission the same query forces an update to the area schedule and every drawing below it.

Treating what stands as though it were approved

The file does not check for deviations. Laid beside the historic permits, the survey map shows a store, a pergola or an enclosed balcony that appears in none of them, and the application stops until the position is regularised or removed. The route for regularising deviations usually adds months.

Reading conditional wording as approval

Phrases such as the committee may consider, or coordination will be required, are read as a promise. They are not: each marks a further stage with its own timetable. The same family includes a deposited plan named in one line, where a design leaning on existing rights alone can reach submission as the position changes.

Common conditions and the time they add

A requirement in the file arrives with a timetable the committee does not control. The ranges are typical and move with the approving body's load.

RequirementWhat it involvesTypical time addedWhat shortens it
Soil surveyTrial boreholes and a soil consultant's report2 to 5 weeksOrdering boreholes as the file arrives, before the basement closes
Fire service approvalA separate document set on its own track3 to 8 weeksSubmitting the day the application opens, not after design review
Traffic consultantParking solution, entrance detail, sometimes a traffic appendix3 to 6 weeksFixing the entrance position at sketch stage
Mature tree surveyMarking, an agronomist's survey and the authorised body's approval4 to 10 weeksRunning the survey before the building position is set
Accessibility specialistAn opinion covering the building and its approaches2 to 4 weeksAdding the specialist before the design is finalised
Antiquities coordinationInspection or supervision in declared areas4 to 12 weeksApplying the day the file arrives, alongside design
Drainage and levelsA signed drainage plan and road level coordination2 to 6 weeksA survey covering pavement levels and gullies from day one

When the file restricts you more than expected

When the numbers fall short of the scheme in your head, the first instinct is to argue, and that is the expensive route. The moves run from cheap and fast to costly and slow.

  1. Check for a technical error: a wrong plot area, an ignored plan, a building line measured from a road axis already laid.
  2. Redesign inside the framework: moving service area, changing the split between storeys, giving up a balcony for a room.
  3. Request a relief: suited to a measured gap in percentages or building lines. It brings publication, an objection window and a hearing, usually 2 to 5 months, plus levy exposure.
  4. Request a non-conforming use permit: where the gap is in use rather than area, granted for a fixed period.
  5. Initiate a plan change: one to three years, justified by substantial volume or outdated planning.

The decision rule between step three and step five is the nature of the gap. An excess in building percentages, height or a building line, at a scale the committee is used to weighing, is a relief. A gap touching land use or dwelling units beyond what the plan fixes is a plan change. The distinction is drawn with whoever manages the application before detailed design is paid for.

There is a quieter option: dropping the element. If the blocked component adds 20 to 40 sq m but delays the permit by half a year and creates levy exposure, the arithmetic does not always justify it.

Checking the file in the first week

  • Compare the plot area in the registry extract, the survey map and the file, and confirm which figure the rights came from.
  • Mark every sentence containing will be required, subject to or conditional on, and gather them into one list with an owner beside each.
  • Check whether a deposited plan is mentioned, and if so obtain its provisions and test both planning states.
  • Cross-check the survey map against the existing permits and mark every structure that appears in neither.
  • Locate the guidelines document the file refers to, even if unattached, and keep a dated copy.
  • List every external approving body and set beside each the earliest submission date allowed.
  • Ask for a massing sketch respecting building lines, coverage and setbacks before floor plans are drawn.
  • Find the expiry date and set a submission target 60 to 90 days ahead of it.
  • Update the budget for the consultants the file requires, with a line for each unplanned survey.

When the information stage justifies separate management

Not every project justifies support beyond the application editor. If one plan applies, no problematic structure stands, and the design stays inside the rights and the envelope, the architect who orders and reads the file is enough. If two plans apply, if there is unpermitted building on the ground, or if an external body imposes its own timetable, the information stage is already running the project.

The gap between the two approaches is measured in money and time. Reading the file properly before drawing opens costs a few consulting hours; one correction round at design review costs 2 to 6 weeks and forces updates at the architect and at every consultant who worked to the previous version, each of whom rejoins the queue.

At Kmo Shetzarich the file is read as a list of conditions before drawing opens: every requirement becomes a line with an owner and a date, and every gap between what the client wanted and what the envelope permits is priced in time and money. Over 15 years of experience, over 1,250 clients nationwide and a 96 per cent approval rate, with a permit in 7 to 45 working days in typical projects. No outcome before a committee can be guaranteed; the quality of the reading in the first week is what you control. To have a file reviewed you can get in touch or call 072-3944444.

Want to know what can be approved on your plot?

Our initial feasibility check is free and carries no obligation. Send us the property details and you will get a straight answer: what can be approved, what needs a relaxation, and what is not realistic on that plot.

You can leave your details in the form or call us directly on 072-3944444. If a file is already open, tell us which stage it has reached and we can point you faster.

96%approval rate on our submissions
7-45days on average to a permit
15+years in building permits

Questions and answers

In most committees the answer returns within 20 to 45 working days, and the clock starts at payment, not at the order. What moves it: whether the survey map meets the authority's format, whether the substance description is precise enough for each department, and whether a body outside the committee must comment. A plot inside a single plan tends to the low end.

The fee is set in the authority's tariff and varies by committee, application type and scale, from a few hundred shekels for a small private application to several thousand for a complex one. The larger cost is what is needed in order to apply at all: a licensed surveyor's map, a registry extract, and sometimes archive retrieval of old permits.

Not on the standard route. The licensing system ties an application to a valid information file, and without a file number there is nowhere to open it, so even an experienced editor stops here. Exempt works and shortened routes exist, defined in the planning and building regulations by type and scale of work. If the work adds area or touches the frame, assume a file is required.

Validity commonly runs around a year and varies between authorities. When it lapses you order again, pay a further fee and need a survey map still in date, and the figures reflect the planning position on that day. If a plan was approved meanwhile, or the guidelines were updated, you may receive different rights, so set a submission target 60 to 90 days before expiry.

It binds in that it defines the conditions your application is checked against, and it is not advance approval of your design. Wording such as the committee may consider is not a promise, and a relief request is examined on its merits after publication and an objection window. Where the file set a requirement and you met it precisely, you have a basis to stand on.

The order is placed in the system by the application editor, the architect or engineer holding the appropriate licence, while you as rights holder approve it and pay the fee. Both steps block progress: without approval and payment the request sits, a common source of two lost weeks. Choosing the editor and the surveyor therefore precedes the information stage.