Our process

Five steps.
No surprises on the way.

Each of the five stages is a gate: it closes on a decision that sets whether the next one opens, and how. This page sets out what is checked at each stage, who holds the file, how long it takes, and what you provide.

3D render of a modular building describing the process stages

Which stage you are at

One document identifies the stage. An address and a land registry extract (נסח טאבו) and nothing more: stage 1. An information file (תיק מידע להיתר) already issued: stage 3, with its validity clock running. Comments back from a reviewer in the national licensing system (רישוי זמין): stage 4, not stage 2.

Why the label matters

Anyone who thinks he is at stage 3 while he is at stage 1 orders the survey before it is settled what will be built, then finds the map lacks a level reading a consultant needs. The second visit adds one to three weeks, by the surveyor's workload and the season.

So every file opens with the same scoping call: what the zoning plan (תב"ע) permits, what stands on the ground, and the gap. That feasibility check is free, and it sets the stage rather than sells one.

The stages

Process Inspection Hq 768x768

Assess & Scope

We learn the project, understand the goal and map the data: plans, previous permits and what exists on site.

Process Strategy Hq 768x768

Build the Strategy

We set the most precise and efficient route, including whether a relaxation or non-conforming use is needed.

Process Coordination Hq 768x768

Collect & Coordinate

We gather documents, order the survey and coordinate every consultant with the others.

Process Submission Hq 768x768

Submit & Track

We file, answer the committee’s comments and handle objections if they arise.

Hero Room Hq 768x702

Permit Granted

We satisfy the permit conditions, hand it over signed - and you can start building.

Stages 1 and 2: before a line is drawn

Stage 1 is reading, not designing: the applicable plans, earlier permits, and past decisions of the local planning and building committee (ועדה מקומית). From them we calculate how much of the building rights is already used, because the balance left governs the design, not the percentage printed in the plan. The arithmetic is in calculating building rights.

The rule that sets the route

  • Rights left over and a design that fits them: the building rights route, no publication, no objection period.
  • Exceeding them slightly needs a relaxation (הקלה); its publication adds one to three months, by the committee's calendar and the objections received.
  • A structure built without a permit goes to legalisation: one application must cover what stands and what is requested.
  • A use other than the plan's designation is non-conforming use (שימוש חורג), granted for a fixed term only.

Stage 2 ends with a written route, a time estimate and a fixed quote. Until you approve them nothing is ordered: the only point where changing direction costs days, not money.

Stage 3: where files stall

Stage 3 is the longest part of most files and almost pure logistics: order the survey, obtain the information file, select consultants and coordinate them. It runs two to six weeks. A file needing only a structural engineer sits at the low end; one adding accessibility, fire safety and traffic sits at the top.

Three failure points that repeat

  • The survey omits a detail a consultant needs later, and nothing can be signed until the surveyor is back on site.
  • The information file is obtained too early and expires before the design is ready. Reissuing costs another fee, another wait, and possibly different conditions.
  • Two consultants sign different versions of one drawing, the reviewer sees the contradiction, and the file returns before planning review opens.

So the order is fixed: survey, preliminary design, and only once the design is stable do we obtain the information file and issue one numbered version to every consultant at once. The document list closes against that plot's conditions, not a general list.

Who does what, and how long

Ranges are working days and vary between authorities. What pushes each to either end is named in the column.

StageWhat we doWhat you provideTypical range
01 Assess and scopeRead the plans, check earlier permits, calculate unused rightsAddress or block and parcel (גוש וחלקה), plus any extract1-5 working days, by how fast records are released
02 Build the strategySet the route, decide if a relaxation is needed, quoteOne decision: approval to proceed2-5 working days once every input is in hand
03 Collect and coordinateOrder the survey, obtain the information file, hold consultants to one versionAvailability for the surveyor, signatures from all ownersTwo to six weeks, by the number of consultants
04 Submit and trackFile, answer comments, handle objectionsLicensing fees to the local authority7-45 working days, by the authority and by publication
05 Permit grantedComplete the conditions, check the signed permit against the applicationThe betterment levy (היטל השבחה) where it appliesDays to weeks, by the conditions in the decision

Stage 4: filing to decision

Filing is a single day's work. What follows is a sequence of reviews, each able to return comments that stop the clock until they are answered in full.

  1. Administrative review: is the file complete, and are the documents and signatures the information file demanded in it.
  2. Planning review: does the request sit inside the applicable plans, the setback lines (קווי בניין) and the balance of rights.
  3. On some applications a design control review (בקרת תכן) is added, testing the engineering against consultant requirements and standards.

What sets the number of rounds

Each round costs time twice: correcting the file, then waiting again in the reviewer's queue. A clean application usually closes in one round; one filed with a known gap runs to two or three, each adding two weeks to a month. That is most of the spread in the 7-45 working day range, unpacked in the permit timeline.

Where publication is required the pace belongs to the publication calendar, not to us. We draft a reasoned response during that window rather than on the day an objection lands.

Before you approve a filing

  • Confirm the information file is valid on the filing date, not only when it was issued.
  • Check that every consultant signed the same drawing, matching on version number and date.
  • Compare the area requested against the balance of rights, not the headline percentage.
  • If a structure on site is absent from the earlier permits, decide whether it enters the application.
  • Confirm the survey reflects the site today, including changes made after the surveyor was booked.
  • Collect signatures from every rights holder, including co-owners who do not live there.
  • Establish the expected fee level at your authority, so payment does not hold up the file.
  • Verify the drawings carry the block and parcel numbers shown on the extract.
  • Where a relaxation is sought, agree in advance whether refusal shrinks the design or not.

Stage 5: what is left

A decision to approve is not a permit. Between them sits a list of conditions set in the decision itself: fees and levies, approvals from outside bodies, appointing a supervising professional. While one condition is open the permit is not signed, even where the planning side was approved in full.

What we check when it arrives

We compare the signed permit against the application line by line: areas, units, height, and every condition written into it. Gaps between requested and approved do occur, usually from a late comment, and it is cheaper to find one before a contractor prices the job off the old drawing.

A permit is not an occupancy approval. Form 4 (טופס 4) is issued on completion, is a separate procedure, and is what allows connection to electricity, water and sewage. Between the two sit inspection stages whose timing derives from the permit conditions, so read those the day the permit arrives.

What a timeline cannot show

Three factors move the schedule and none is ours to control: the pace of the local authority, consultant availability, and the pace of your decisions. The same application can close in half the time at one authority and wait twice as long next door, on how many reviewers it employs and how often it convenes.

Consultant availability funnels on most files into the structural engineer and the accessibility consultant, whose queues are the longest the file has to join. One running late delays not a single signature but the whole set, because the file is submitted as one package.

A decision left open two weeks on your side, whether to add a room or drop it, halts the consultant chain: all of them design on the same drawing, and none can advance on a version that may change.

We do not promise a date. We commit that no day is lost on our side, and that you know which stage the file is at. Where time is the binding constraint, the fast-track route is built around it.

Questions and answers

Two clocks. Preparation, stage 1 to filing, runs two to six weeks, moved by surveyor and consultant availability. The authority clock runs 7-45 working days on most files we submit, pushed to the top by publication and by a second round of comments.

Licensing fees go to the local authority at stage 4, separate from our fee. The amount follows the area requested and varies between authorities, so the quote estimates it. Late payment delays the file opening for review. The betterment levy, where it applies, is a stage 5 condition.

In most cases, no. We represent the file before the reviewer and the committee. You are needed for an objections hearing where the committee wants the owner directly, or for a signature that cannot be delegated by power of attorney. We tell you in advance and attend with you.

That is normal, not a failure. Comments are a list of required corrections, and the file waits until they are answered. We handle them with the person who wrote them, so we know what is missing before correcting. A full answer usually closes in two weeks to a month; a partial one generates another round.

Not skipped, but stages can run in parallel. The survey and the information file can start alongside preliminary design, and consultants can be selected before the design closes. What cannot run in parallel is signing a drawing that is still changing, because every change forces everyone who signed to sign again.

We choose and coordinate; you pay the consultant directly. The consultant then works to one uniform brief, and there is no hidden incentive in the choice because we take no commission. An architect or engineer you already use joins the file, at a cost that sits outside our fee.

It depends when. At stage 2, before the survey and consultants are engaged, a change costs a few days. At stage 3 it forces every consultant who signed to sign again, adding one to three weeks. After filing it produces an amended application and can send the file to the end of the queue.